BuildBIM in collaboration with Construction Workshop and Atmos Engineering carried out modeling and coordination in the areas of Gastroenterology and Intensive Care Unit.The project had an investment of 15M NZD, including two critical and highly dependent areas within the hospital.

 

The project was particularly complex because the remodeling work that had to be done while the hospital was still running. Working together with Naylor Love,  the main Service Coordinator, BuildBIM made the detection of critical interferences between the architecture, steel structure and existing services, in addition to developing the modeling of the HVAC specialty, and then delivering the manufacturing planimetry and as -builts for the reception of the project.